Plotting a Path

Nov 1, 2000 12:00 PM, By Cheryl Humann and Umang Taylor

Budget modeling and early cost estimating help schools control spending on construction projects.

After the last nail is driven and final block of concrete is poured, the success of a school or university's construction project often is measured on the bottom line: Was the project within budget?

Education projects are under increasing pressure to control costs. Staying within budget is important not only to the project at hand, but also for future projects. A school district with a track record of controlling and managing construction costs will have a better chance persuading taxpayers to support a bond election for school construction. Two strategies school districts can use to control and manage construction costs are budget modeling and early construction estimating.

Budget modeling identifies all the funding for a project and allocates those funds to expenditure categories to determine a construction budget. To determine the construction budget, the expenditure categories are identified and grouped into either soft or hard costs.

Soft and hard Soft costs are those expenditures necessary to complete a project but not directly "bricks and mortar," such as design and consultant fees, communications costs, interim housing, moving or relocation costs, and additional district staffing.

A primary soft-cost category is fixtures, furnishing and equipment (FF&E). During the planning stages of a project the soft costs usually are allocated as a percentage of the total project budget. As the planning and design of a project progresses, the percentage can be increased or decreased.

The hard-cost categories are the bricks and mortar of the project.

The construction budget can be subdivided further. In some cases, state and local governments require schools to spend a certain percentage of the construction budget on accessibility items or to isolate the cost of a portion of a project that may be joint-use or funded separately.

Early, accurate and continual feedback on estimates will help keep the design on track and within budget. Once a school determines the construction budget, it can use many methods to prepare cost estimates. The stage of design often determines the method.

In the early stages of planning, estimates are completed using strictly a square-footage and building-system basis. As the design phase progresses, the estimates are prepared as defined by the Construction Specifications Institute (CSI). Detailed cost predictions are based on the quantity of specifications and building materials, and are refined through the schematic design, design development and construction document stages to reflect new input from the design and management team.

Unique issues Education construction projects have unique characteristics that need to be considered when estimating cost.

- System selection: As a design team incorporates district requirements and selects the best systems available, the cost of those systems can affect a project significantly. A good example is the cost of technical systems; the selection of the technical system also affects the building electrical system and the FF&E budget. The cost of the three components of the technical systems can range from $6 per square foot to $18 per square foot.

- Time constraints: Time restrictions that a school places on a construction team can affect costs directly. For example, summer is the peak construction season, and simple supply-and-demand economics lead to higher costs to find available workers. Accelerated schedules to abide by time constraints may require shift and weekend work and may lead to cost escalation. In addition, accelerating the schedule will affect material and delivery schedules and may increase their costs.

- Site safety and security: Because of the nature of children's curiosity, schools need to plan their construction projects especially carefully. School construction sites may need fencing and barriers that wouldn't be required for other projects. These safety precautions need to be incorporated into the estimate as early as possible.

- Joint-use project: With the growing trend to have schools serve as community centers, the operation of a facility during the day may be different than in the evening. Schools should determine whether they will need additional security systems because of this difference in operations, and incorporate the costs into the construction estimate and the future operations budget.

The keys to a successful project lay in a well-thought-out concept, tenacious preplanning, and accurate budgeting and estimating. The process is best executed with a team that consists of a school representative, design consultants with experience in education, and a builder. By involving these experts throughout the planning, designing and construction phases, the school is better able to deliver the project on time and within budget.

Estimating the costs of a project normally includes the following elements:

- General requirements, modifications and procedures.

- Site preparation, earthwork, utility piping materials, water distribution and improvements.

- Foundation concrete and other concrete pads.

- Masonry, concrete block work and retaining walls if required.

- Structural metal framing, joists, decking and fabrication.

- Waterproofing, insulation, fire stopping, manufactured roofing and riding, roof specialties and accessories, and joint sealers.

- Metal doors and frames, wood and plastic doors, special doors, hardware and glazing.

- Gypsum board, tile, acoustical treatment, special ceilings, surfaces, carpet, special flooring, painting and wall coverings.

- Compartments and cubicles, flagpoles, identifying devices, lockers, fire protection, storage shelving, toilet and bath accessories.

- HVAC, fire protection, plumbing, air distribution and controls.

- Switchgear and panels, service and distribution, lighting, communications, smoke detection, electric resistance heating, and conduits for telephone and data lines.

- Landscaping and off-site work.

Most Recent Story

Armed and Dangerous

Mike Kennedy

Just when you think you've heard everything! A lawmaker in Nevada plans to introduce a bill this month that would allow teachers to carry guns in classrooms. (Yes, you read that correctly.)

Most Popular Articles

Subscribe to RSS headline updates from:
Powered by FeedBurner

Essential Reading

The Subtle Stuff

Vikas Nagardeolekar and Edwin Merritt

It's hard to win passage of a school construction bond — whether through a citizen referendum or the vote of a town council or general town meeting.

Hear and Now

Michael McKeon and Lincoln Berry

When acoustics are mentioned with regard to schools, many people first think of performing arts.

Making it Readable

Peter Gisolfi

When my daughter was 10 years old, she left the comfort of her elementary school for the unfamiliar territory of the middle/high school building — a crazy quilt of pieces from the 1910s, 1930s, 1960s and 1970s.

Echo Boom Impact

Phillipe Dordai and Joseph Rizzo

Like their baby-boomer parents, the echo-boom generation is reshaping the college and university landscape.

Spotlight On:

Now Accepting Entries Architectural Portfolio 2008. Entry forms due June 3. VView more information on the 2008 Architectural Portfolio.

Top 10

How does your institution rank? Including enrollment and expenditures, growth rates and more!

AS&U 100

American School & University highlights the largest 100 school districts each September| Who's growing and who's slowing

Back to Top

Browse Back Issues

ASU April Cover ASU March Cover ASU February Cover ASU January Cover ASU December Cover ASU November Cover ASU October Cover
BROWSE BACK ISSUES